SAMPLE This page is a SAMPLE – illustrative, not a live issue. It is not delivered to subscribers and is not refreshed after publication. Content and figures below are drawn from Sol Associates’ real weekly digest of 15 September 2026, reused here to show format only. For the current, live-issue experience, join the beta.

Data as of 15 September 2026

Market Snapshot

Romanian wind and solar output stayed within normal seasonal bands this week. Grid balancing costs eased slightly from the prior week as reserve margins improved. Battery storage tenders in the public procurement channel continued at a steady pace, consistent with the ramp seen since the second quarter of the year.

Data snapshot The ATR (grid connection approval) register chart below is a snapshot dated 30 September 2025. It is not live and will not be refreshed on this sample page – the real weekly issue rebuilds this chart from the current register each week. Source: Sol Associates ATR register extract, outputs/grid_registers/atr_tidy_2025-09-30.csv, compiled from public ANRE/Transelectrica Avize Tehnice de Racordare filings.
ATR-approved capacity by technology, Romania Horizontal bar chart of ATR grid-connection-approval capacity in megawatts by technology: PV 11,183 MW, Storage 9,414 MW, Conventional 9,099 MW, Wind 3,310 MW, Hybrid 1,327 MW, Hydro 342 MW. Snapshot dated 30 September 2025. ATR-approved capacity by technology (MW) PV 11,183 MW Storage 9,414 MW Conventional 9,099 MW Wind 3,310 MW Hybrid 1,327 MW Hydro 342 MW Six largest technology categories shown; Thermal, Cogeneration, Biogas, Consumer and DSO-works rows excluded for readability (all under 1,000 MW each). Source: outputs/grid_registers/atr_tidy_2025-09-30.csv (public ANRE/Transelectrica ATR filings), snapshot 30 September 2025, compiled by Sol Associates.

Regulatory Watch

Regulatory Watch

ANRE published updated guidance on connection guarantee thresholds for new grid applications, tightening the collateral requirement for projects entering the queue after the effective date. Transelectrica’s public document library shows two revised technical files for the national transmission plan, both published this week. No material change to the grandfathering rules for previously issued connection agreements was announced.

Most recent ANRE licence and authorisation grants on the public register, pulled 15 September 2026 (latest recorded issue date in the pull: 9 September 2026). Source: outputs/anre_licente/licente_autorizatii_2026-09-15.csv, ANRE public licence portal (portal.anre.ro/PublicLists/LicenteAutorizatii). Company names and counties as published; natural-person rows excluded.

Company County Type Activity Status Date issued
Faget Storage SRLTimisAutorizatie de InfiintareProducereAcordata2026-09-09
Eco Trading EnergyBucurestiLicentaProducereInregistrare Dosar2026-09-08
Apollo TradingConstantaLicentaFurnizareAcordata2026-09-03
Boro SolarBucurestiAutorizatie de InfiintareProducereAcordata2026-09-03
Eco Wind SalbaticaBucurestiAutorizatie de InfiintareProducereAcordata2026-09-03
Energy Storage SolutionsBucurestiAutorizatie de InfiintareProducereAcordata2026-09-03
Falcon WindBucurestiAutorizatie de InfiintareProducereAcordata2026-09-03
Green BreezeBucurestiLicentaProducereAcordata2026-09-03
JR Repono SixIalomitaAutorizatie de InfiintareStocare EEAcordata2026-09-03
Kronospan TradingAlbaAutorizatie de InfiintareProducereAcordata2026-09-03

Grid Watch (illustrative)

Grid Watch – a simplified read on the 400 kV backbone

The full weekly issue includes a Grid Watch section reading on connection queue and transmission capacity. Below is a simplified, honestly-scoped schematic – not a full national topology – showing a handful of the largest 400 kV connection points by ATR-approved capacity, based on the same public register used for the chart above. Node size is proportional to approved capacity; this is a schematic, not a geographic map.

Verified vs. simplified Node names and MW figures are real and drawn from the ATR register snapshot (30 September 2025) cited above. Their positions on this diagram are schematic only – not to geographic scale, and connecting lines represent that these are all part of the same public 400 kV register, not verified physical circuit routing.
Simplified schematic of major 400 kV ATR connection points Seven named 400 kV substations from the public ATR register with approved capacity: Tantareni 1,980 MW, Urechesti 1,320 MW, Cernavoda 707 MW, Darova 691 MW, Stupina 513 MW, Sagu 488 MW, Medgidia Sud 466 MW, shown as a schematic, not a geographic map. Tantareni 1,980 MW Urechesti 1,320 MW Cernavoda 707 MW Darova 691 MW Stupina 513 MW Sagu 488 MW Medgidia Sud 466 MW Based on public ANRE/Transelectrica ATR filings, as of the 30 September 2025 register snapshot. Node size proportional to approved capacity (sqrt scale). Schematic only, not a geographic or single-line diagram. Source: outputs/grid_registers/atr_tidy_2025-09-30.csv, compiled by Sol Associates from public ATR filings.

Tender Activity

Tender Activity

Public procurement notices tracked via data.gov.ro’s open tender datasets show a modest increase in energy sector award activity compared with the prior four week average, concentrated in grid support equipment and site preparation works. Total disclosed award value for the week stayed well within normal bounds.

The full weekly issue also covers Contractor and Competitor Watch, Grid Watch, Weather and Yield Context, and Sol’s own read – see what is inside every issue. SEAP Radar subscribers get the row-level tender feed behind this summary – see a sample tender row illustration.

Disclaimer and Sources

Disclaimer

This digest is produced for general market awareness purposes only. It is not investment, legal, tax, or regulatory advice, and it should not be relied upon as a substitute for professional advice tailored to a specific situation. Sol Associates makes no representation as to the completeness or continued accuracy of any figure after the publication date, and accepts no liability for decisions made on the basis of this document.

Attribution and Sources

Figures and regulatory items in this digest draw on public data from data.gov.ro, ANRE, and Transelectrica. All data is used under each source’s applicable public data terms; no confidential or client specific information is included in this document.

  • SAMPLE – illustrative, not a live issue. This page reuses a real digest dated 15 September 2026 to show format; it is not part of the live weekly send and is not refreshed.
  • No investment, legal, tax or regulatory advice – general market awareness only.
  • Public sources only – no confidential or client-specific information appears in Sol Signals, ever.